JOINERY PROJECT TIMELINES.
The Production & Installation Timeline below serves as an approximate guide for your project’s duration. Please note that timelines may be influenced by factors such as material availability, third party trade scheduling, and weather conditions. For larger projects, works may be delivered in stages (e.g. Kitchen & Robes as one stage, Laundry & Vanities as another).
Please note:
Any variations may extend the overall timeline and will only be actioned once formally approved and signed.
End-of-year projects may exceed the estimated timeframes below due to seasonal demand.
All durations provided are approximate and subject to change, as each project is managed on a case-by-case basis.
This timeline serves as a general guide based on our current workload.
Last updated: January 2025
Final Construction Plans
1–2 weeks
The finalisation and signing of your detailed Construction Plans can only commence once all client selections (e.g., handles) have been completed and all required information has been provided to Gull Design. The timeframe outlined below reflects a typical process; however, please note that this stage is largely client-driven and may vary depending on the timeliness of your selections and submissions.
Production
This refers to the period between the submission of final construction plans and the point at which the project is ready for production in our factory.
6–7 weeks
Laminate (colour board) Projects
8 weeks
Two Pack Projects
9 weeks
Shaker Style Projects
Additional Time Required (TBA)
Veneer & Solid Timber Projects*
*Timeframes for veneer & solid timber projects depend on material type and availability.
Post-Installation (Other Trades)
The following times start after a standard installation is completed.
5-7 working days
Stone Benchtops
5-7 working days
Solid Surface Benchtops
10-12 working days
Stainless Steel & Brass
10-12 working days
Glass Tops & Splashbacks